OAMLConfiguration Management Item (CMI) Processing Time Line
Maximum: Funding / Technology Dependent
PECP Submission START the CLOCK T = 0
Approval of PECP at SRB Meeting T = 0
Delivery to OAML CCC @ 6 months to deliver
CCC QA Verification (in-house) T= @ 2 months
And Validation if “New” proposal (CIMREP / CIDREP)
N096 Accreditation (New items only) T = 2 weeks
Configuration Item Available for Distribution
(CCB Directive and Formal ECP Approval, and
Media and Documentation Preparation) T= @ 1 month
All time allotments are based on actual “best-case” records